General Designer

Omorika Montenegro

 

STAGE 1

Reconstruction of Lazaret historical building and embankment, construction of yacht club

Construction works are carried out in accordance with the following documents:

  • The decision of Construction Directorate of the Ministry of Tourism and Sustainable Development №UPI 0503-852/15-2015 from 12.02.2016

  • The decision of the Secretariat for Spatial Planning and construction of the Municipality of Herceg Novi, Montenegro №02-3-361-90/2014 from 17.06.2014

Planned completion: Q2 2018

 

STAGE 2

Construction of Marina, Residence building with a shopping centre and underground parking, spa centre with two swimming pools. Construction works are carried out in accordance with the following documents:

  • The decision of Construction Directorate of the Ministry of Tourism and Sustainable Development №UPI 1054-1000/10 from 23.12.2016

  • The decision of Construction Directorate of the Ministry of Tourism and Sustainable Development №UPI 1054-1001/22-2106 from 14.03.2017

  • Urban-technical conditions for the construction of a hotel complex Lazaret in  Meljine adopted and approved by the Directorate for the construction of the Ministry of Tourism and Sustainable Development of Montenegro (№0503-1390/17 from 01.09.2015)

Planned marina opening: Q3 2018

Planned Residence opening: Q4 2020